Client: Cameco, Key Lake Mine

Duration of the Work: 281 days

Area of Work: Electrical & Instrumentation

Comments: Installed 15 kV Power Cabling including terminations and connections. Installed 600 V Control Cabling and terminations. Installed MCC’s, Stand Alone VFD’s, Dry-type Transformers, Distribution Panels, 15 kVA redundant UPS system, disconnect switches, and welding receptacles. Installed numerous fluorescent and emergency lighting fixtures, heat trace, and sump pumps. Installed Cable Tray complete with fireproofing and grounding. Installed Grounding Rods complete with cable terminations and connections.

Proof Digital

Proof Digital was founded in 2013. The company, then known as "unINK Marketing & Creative Agency," was focused on building websites, providing graphic design services, and assisting businesses in running digital advertising campaigns.

Today our work is more reflective of a digital consultancy than a marketing agency. Marketing is still very much included in the scope of services we provide; however, we focus on the uniqueness of our clients to identify areas where technology can create a competitive edge and deploy scalable solutions that are cost-effective with high impact.

AI, automation, custom web applications, and data services are the core of most of our work. Over the past four years, we have built a large code stack that allows us to deploy creative products that leverage our clients' data (sales, inventory, accounting data, HR, and more).

https://proofdigital.app/
Previous
Previous

Cameco | Propane Farm Expansion MPEI

Next
Next

PCS Lanigan | Freight Elevator Replacement