Cameco | South Freeze System Electrical & Instrumentation

South Freeze System Electrical & Instrumentation2.jpg
South Freeze System Electrical & Instrumentation1.jpg

Client: Cameco, McArthur River

Duration of the Work: 221 days

Area of Work: Electrical and Instrumentation Installation

Comments: Components of the work include the installation of electrical cable system, electrical cables, grounding system, electrical heat tracing and equipment. Also the installation of instrumentation, cables, junction boxes, control and communication cabinets and CCTV cameras.

Proof Digital

Proof Digital was founded in 2013. The company, then known as "unINK Marketing & Creative Agency," was focused on building websites, providing graphic design services, and assisting businesses in running digital advertising campaigns.

Today our work is more reflective of a digital consultancy than a marketing agency. Marketing is still very much included in the scope of services we provide; however, we focus on the uniqueness of our clients to identify areas where technology can create a competitive edge and deploy scalable solutions that are cost-effective with high impact.

AI, automation, custom web applications, and data services are the core of most of our work. Over the past four years, we have built a large code stack that allows us to deploy creative products that leverage our clients' data (sales, inventory, accounting data, HR, and more).

https://proofdigital.app/
Previous
Previous

Cameco | Freeze Facility & Brine Pumphouse Erection

Next
Next

Cameco | Potable Water Line & HDPE Piping Tie-ins